Solar installations require a Factory License Amendment (รง.4).
The procedures for the application are as follows
- Document Preparation: The entrepreneur prepares all necessary application documents for the solar system installation.
- Submission: Submit the application to the Provincial Industry Office (PIO).
- Verification: The PIO reviews the documentation and officially accepts the application.
- Public Notice: A public announcement must be posted for at least 15 days to gather community feedback and opinions.
- Public Opinion Summary: The PIO summarizes the results of the public hearing process.
- Fee Payment & Approval: The PIO instructs the entrepreneur to pay the required fees and issues the formal Certificate of Factory Expansion.
Key Requirements to Note
- Threshold for Solar Expansion: A factory is required to apply for an expansion permit if the solar installation capacity is 1 MW or higher.
- Definition of a “Factory” (Ror.Ngor. 4): Under current regulations, a facility is classified as a factory requiring a license if it utilizes machinery exceeding 75 horsepower and employs more than 75 workers.

ทีมผู้เชี่ยวชาญ Solar PPM ประกอบด้วยวิศวกรพลังงานแสงอาทิตย์ที่ผ่านการรับรองและผู้เชี่ยวชาญด้านอุตสาหกรรมโซล่าเซลล์ที่มีประสบการณ์จริงมากกว่า 10 ปี ครอบคลุมทั้งการออกแบบ ติดตั้ง และบำรุงรักษาระบบโซล่าเซลล์ ในฐานะส่วนหนึ่งของบริษัท โซลาร์ พีพีเอ็ม จำกัด ซึ่งอยู่ในเครือบริษัทมหาชน PORN PROM METAL ทีมของเราได้มีส่วนร่วมในโครงการติดตั้งรวมกว่า 200 MW ทั่วประเทศไทย ให้กับลูกค้าชั้นนำอย่าง Central Pattana, Thai Union, IKEA และ HOYA